Pedal to the metal

As promised, a catch-up on what I’ve been up to.

RDI came and insulated the loft and moved the oil tank.

They also put the pipework in ready for the radiator to be moved once Pete and Al were free to sort the wall out.

Once the oil tank was out, Alan and his team could remove the garage.  As my neighbour walks his dog around the back, they made a temporary fence out of some of the old picket fence lying around.

Warren, who harled the chimneys down at Ethel’s, will be along at the beginning of November to harl the wall.

I started clearing the garden.  It’s mainly blackberries, blackcurrants and honeysuckle.  The idea is to keep enough hedge behind the oil tank to grow over it and hide it a bit, clear a space behind that to put a picnic table so you can see the view between the two houses, and then clear all the way around the fence line, so that the wall can be taken down onto my garden and a new fence erected.  My neighbour says I’m fine to take a digger around the back to put posts in as long as I don’t leave any stones that will clog up his mower.  It’s tough going!

Inside I’ve been peering under more bits of carpet and the more I see of the downstairs floor, the more I love it.

Howdens’ designer, Tom, and I have been back and forwarding by email.  We’ve got the kitchen and utility price down to £7,500 from £12,000, but Tom just wanted David to double-check his measurements and make sure the wall cabinet doors in the kitchen would open under the beams.  So on Wednesday afternoon I picked David and Magnus up from Bettyhill and we all went over together, Magnus to look at the external woodwork and inside walls for painting surfaces.

David noticed pretty quickly that two of the beams in the maid’s room had been boxed in before they’d been papered.  A quick prod with a hammer and crowbar later and we found a beautiful natural rough beam, which must have been hewn nearly 100 years ago.  A bit of bark fell off it.

David also took a look at the mystery brick wall and agreed that it almost certainly wasn’t load-bearing and I asked him to look at the joists in the bedroom we’re turning into a bathroom upstairs – the good news is that as long as I put a bath perpendicular to them (which I was planning to do anyway) and I don’t buy a cast iron one, they’ll take the weight.  Upstairs has had 18mm chipboard laid over the original floorboards, which is good news for putting Karndean down in the upstairs bathroom (less floor prep required) and as Jeff remembered, there’s a decent depth under there to get plumbing in.

Next week we start to get busy.  On Wednesday Green & Cameron arrive to rip out the grass at the front, replace it with gravel and drop the kerb to create the parking spaces.  On Friday RDI come back to move the radiator – Pete and Al haven’t had time to sort the wall, but I need the heating back on, so we’ve agreed they’ll put an isolation valve on each side and then Pete can take it back off when we need to get behind it.

Magnus and David both recommended an electrician – sadly Dougie is tied up on a massive job all winter and can’t help me this time – but warned me that he’s getting close to retirement and doesn’t always want to take on big jobs.  I was hopeful that since he lives fairly close to Coldbackie and could have a key and do it at his own pace, he might be persuaded and although he hasn’t said yes yet, he is at least coming to have a look at it towards the end of next week.  I also have a plumber interested, who’s going to stop by when he’s next out west.  He’s working with David on a bathroom near me soon, so hopefully he’ll drop in at the same time.

In the meantime, I’ve been working on room layouts.  All the bedrooms, the upstairs bathroom and the living room have been mapped at 1:10 scale in Excel (with the cells made into squares) and then I’ve created shapes to the correct dimensions for beds, bedside tables, sofas and so on.  I’ve also marked where the existing sockets are and where I want new ones.

Next week’s job is to think about colour schemes.  I found a copy of Farrow & Ball: How To Decorate* in the local library system, took it with me when I went away with my mum last week, and read the whole thing in two days.  It’s been so, so helpful.  I’ll leaf through it again next week as I’m starting to work out what colours I want.  The only thing I’m firm on at the moment is that I want a big dark wall to hang pictures on in the stairwell, but it really does feel like we’re about to start making some speedy progress.

 

Floored

Firstly, if the Highland Council is still reading, thank you very much for putting the council tax back down to the 100% rate.  I will do my utmost to get the house finished and onto business rates by the end of the council tax year!

David has been in for a day and a half this week and now we have a floor upstairs.

Twin bedroom – turns out that the underfloor heating plus 18mm chipboard (turns out we hadn’t ordered 22mm after all!) was exactly the right height to match up with the 3 x 2 round the window.

Hall – this will be covered up by a cupboard.

Double bedroom

Single bedroom

I had a bit of a scrub at the bannisters, just to see how easy it was going to be to sand the paint off.  The bannisters themselves should be fine, but the understairs cupboards not so much – I can see about three layers of paint there.  Fortunately Mick has a sander, so I won’t have to do it all by hand with sandpaper.

Today has been a sheep-wrangling day – our area is bad for liver fluke, so since my brother-in-law was staying, we took advantage of the extra pair of hands to get them penned up and dosed.  Two brothers looking very pleased with their herding efforts!

They also hung gates in the gateways between the three fields (they’d been removed before we bought the crofts), so catching them next time might be a bit easier, as I’ll be able to at least confine them to the small field rather than having them racing around all three when they escape!

Post-Christmas progress

WARNING:  lots of pictures ahead!

One of the things I forgot to mention in my last post is that the Highland Council decided to give me a Christmas present of putting me back on 200% council tax as of 25th December.  I’ve sent them an email explaining that the house still isn’t done and attaching scans of the latest bunch of invoices and letting them know they can follow progress on this blog, so hello to the Highland Council council tax department if you’re reading this 🙂

So, what’s been happening in the last fortnight?  The stove arrived:

and Pete and James turned up to put the replacement hearthstone in, very, very carefully!

David’s put all the internal studwork back in, has been panelling like a demon and has also replaced all the rotted/woodworm-y floorboards.

We hit a bit of an issue last Friday.  We were forecast gales on Thursday night, not particularly high – gusting to about 65mph or so.  As I was walking down to feed the sheep on Friday morning I saw an SSE van in the village and a flapping power cable.  ‘Wonder what caused that?’ I thought.  The next field I passed was Ronald’s, who lives in the house diagonally opposite Ethel’s.  There appeared to be a heap of twisted metal in it.  ‘Crumbs, some poor sod’s lost their roof,’ I thought.

Er, yes, that poor sod would be me – the haybarn roof had completely gone!

Talking to the SSE guys, they said it looked like it had come off in one piece, bounced off the power cable between Ethel’s house and Ronald’s with such force that it snapped four cables as a result, knocking out power to that end of the village, and then bounced in Ronald’s field, breaking up on impact.  In the picture of the field, you can just make out a piece of wood stuck vertically in the ground to the left of the telegraph pole.  That had driven in over a foot deep.

Mick came home from work and we cleared out all the wood from the stalled byre, finding the chains for tethering the cattle in the process – there’s a selling point!  “If your children misbehave whilst on holiday, simply tether them in our handy cattle stalls…”

And I really must take this sofa to the tip.  Ethel got it for the front room, but decided it was too big, so it’s been living in a cattle stall ever since.

Anyway, the hay is all safe and sound, the wood is in the roofless hay barn and we’ll get a new roof on it once Mick has decided whether or not he’s going to rebuild the front wall, which is bowing out a bit.  Back to the house.

David, bless him, came over on Saturday to finish the last little bits he needed to get done before the heating team started.  I am LOVING the way the bedroom alcoves have turned out – how’s this for a bedroom with a view?

Derek turned up on Monday with his team and Dougie was on hand to wire up the manifold.  Heating is now going in 🙂

Holes are starting to appear for sockets and switches.

And once the pipework is done for the bathroom, the last bit of plasterboarding can be done.

So it’s just finish the heating, get the floor down, install the kitchen and bathroom, decorate it and make a garden.  Easy-peasy, right??