Starting to feel like we’re getting somewhere

I’m not quite sure how it’s got to be Thursday already, but this week has passed in a blur and Pete, James and Connor have got an awful lot done.

The kitchen has been plastered:

156 armadale - kitchen - 18

coated with bitumen:
156 armadale - kitchen - 17

and then the liner was put down and the concrete floor re-poured. Try getting through THAT, damp!!
156 armadale - kitchen - 16

The same’s happened upstairs in bedroom one (minus the floor liner), as that gable end faces the sea and takes a battering:

156 armadale - bedroom one - 21

156 armadale - bedroom one - 20

And they’ve also sorted out that wobbly stone under the window:

156 armadale - bedroom one - 19

and picked and pointed the gable end in bedroom two (I’ve decided to keep that fireplace as bare stone and not put the little surround back in, by the way):

156 armadale - bedroom two - 10

So the inside is more or less ready to hand over to Dougie and David, once the floor’s set in the kitchen – only we’re having trouble tracking down David!  The problem with using someone widely acknowledged to be one of the best joiners in the area is that he’s very in demand.  Pete could really have done with him here this week, but we think he’s been working down at Forsinard where there’s no mobile signal, as no-one’s been able to speak to him.  By ringing his home number at 9pm last night, Pete finally managed to speak to his other half, so fingers crossed he might be able to start with us next week, as Dougie will be back and ideally we want the studwork to go up for the wiring to be run down (and I need to know whether he’s using 3×2 or 2×2 so I know what thickness of insulation to order!)

Outside there’s progress as well.  The scaffolding is up on the back and the roof tiles are off:

156 armadale - outside - 8

156 armadale - outside - 5

156 armadale - outside - 6

That membrane does make it rather blue inside!

156 armadale - bedroom three - 5

And after a long weekend down the road at our neighbour’s house after they were delivered to the wrong address on Friday, Travis Perkins came back on Wednesday and brought the roof slates up:

156 armadale - outside - 7

And, of course, one of the most important bits – care and feeding of your roofing team!  It was cheese and chive flapjacks today:

baking - cheese and chive flapjacks

I also had a visit from ERG today to quote me for the windows and door.  Before they arrived, I looked out the paperwork from when ours were done three years ago and noted that 2 doors and 10 windows came to £8,800 – so considering that I was wanting 1 door and 5 windows, my estimate in the budget of £5,000 seemed about right.  Er, no, their prices have gone up a bit.  List price £8,300, 20% returning customer discount brought it down to £6,640.  I made the time-honoured tradesman ‘suck-through-your-teeth’ noise, he asked how much I was hoping to do it for and we ended up shaking hands at £5,812.  The surveyor should be coming round in the next two weeks to measure up more accurately and then it’s 6-8 weeks for manufacture and delivery, which will be about right for my schedule.  The front door will be dark green outside, white inside and part-glazed.  The windows will be white inside and out, with oak window sills and door and window furniture will be silver.  Once the exterior is painted just off-white, it should look pretty smart!

Tomorrow Callum is coming to sweep the three chimneys.  I’m not sure how many years it is since they were last done, but Derek the heating engineer made the same suck-through-your-teeth noise when he looked up the living room one as we were discussing the woodburner, so I think it’s going to get messy….

I came in like a wrecking ball

So Pete the Roofer stopped by, as promised, and we now know what we’re doing with the roof.  It’s going to be done in 16×8 heavy slate (we have at least one storm that goes over 100mph a year and it’s probably the most exposed house in the village), capped with plain buff ridge tiles.  The velux at the front will be enlarged to the same width as the front door and made to line up with it (it’s slightly off to the right at the moment, which my slightly OCD husband hadn’t noticed until I pointed it out today and it’s now driving him nuts!), similarly the velux at the back will be enlarged and lined up with the bathroom window (ditto!) – although I’ve said that if doing that means it’s not evenly-spaced with the two new ones we’re putting into the other bedrooms, then I’d rather have them evenly spaced across the roof than vertically aligned!

After lunch we got started with the work.  Since the roof is going to get done first, we need to get all that panelling stripped out of the upstairs bedrooms.  This is what we started with:

20150728-IMG_9183

156 armadale - bedroom one - 1

156 armadale - bedroom one - 2

And three very enjoyable hours spent with a pry bar and a hammer later….

156 armadale - bedroom one - 3

156 armadale - bedroom one - 4

156 armadale - bedroom one - 5

156 armadale - bedroom one - 6

Interesting things we’ve discovered today:

  1. That little cupboard (which I am so pleased I’ve been able to keep – the door is safely stowed away for reattaching later) is sitting on top of the house wall.  Everything above the level of its base is the gable end and the depth of the cupboard thinner!
  2. No fireplace 🙁  I was hoping we’d uncover a matching one to the one in the other large bedroom, but sadly not.
  3. There is a BIG wet patch on that wall – literally dripping water, which was slightly concerning, but as we got more of the panelling off we realised it was confined to the centre and a quick look outside confirmed that the harling is fine – so we’re pretty sure that the leak is coming through the chimney, which we’re going to get repointed while they’re up doing the roof anyway.
  4. Where the panelling changes colour to the dark brown in the third picture (there’s a bit of brown door, then about three painted bits of panel, then the darker) is the amount of length we’ve added to the room by taking out the two cupboards.  The mirrored door has been saved to go back on a little box cupboard around the hot water tank.

All in all, a good first day.